Welcome to Dreamsmith Ink

Services to the Written Word

 

Structural Steel Construction Standards/ Caryn Leschen, technical writer

IRONWORKER CODES OF SAFE PRACTICES

: Structural Steel Erection and Construction

A. Ironworkers who engage in erection and construction are governed by Article 29 of Title 8, California Code of Regulations, including but not limited to the following specific requirements. A complete copy of these regulations can be found on the Internet at http://www.dir.ca.gov/. Search on the regulation number you wish to view.

B. This document and the documents it refers to spell out the safety requirements necessary to protect employees from the hazards of steel erection activities. These activities include the construction, alteration and repair of single and multi-story buildings, bridges and other structures where steel erection occurs. Additional requirements may be found in Article 20, Section 1635(b).

1. Ironworkers are defined as employees who engage in multistory building steel erection and engage in the following activities:
a. Hoisting, connecting, landing, placing, installing, welding, bolting or rigging structural steel, steel joists, metal buildings, metal decking, siding systems, ornamental iron, miscellaneous other metals and similar materials.
b. Working under loads.
c. Moving from point to point to perform these activities.

2. Ironworkers are also defined as those who are, while on the job, placed at risk of any harm or hazards due to (B1.) or column instability, double connections, or falls to lower levels, and are subject to these safety measures.

C. Erection of structures is governed by §1710 of Title 8, California Code of Regulations, which are outlined below. A list of definitions of terms is available in §1710 (3b.) of Title 8, California Code of Regulations.

D. Where a building is being constructed in sections, each section constitutes a building.

E. No person shall proceed with any work assigned to him or require any other person to perform any work unless these safety measures are in place.

: Site Layout and Construction Preparation

A. Before authorizing commencement of steel erection, the Contractor shall ensure that the [Company] is provided with written notification that:
1. The concrete in the footings, piers, and walls and the mortar in the masonry piers and walls has attained sufficient strength to support the loads imposed during steel erection.
2. All repairs, replacements and modifications to anchor bolts were conducted in accordance with the standards of **§1710 (f2).**
3. Adequate access roads into and through the site for the safe delivery and movement of any vehicles or machinery are being maintained as passageways for pedestrian and vehicular use.
4. A safe, graded and properly drained area is readily accessible with safe storage for and adequate access to equipment and material.
5. All hoisting operations meet the requirements of the General Industry Safety Orders, Section 5002.

B. The sequence of erection, bolting, guying, riveting and welding shall be such that the stability of the structure is guaranteed at all times; this applies to:
1. The dead weight of the structure.
2. The weight and working states of all equipment placed on it.
3. Any external forces that might be applied.

: Hoisting and Rigging:

A. The crane or derrick operator has authority over their operations; if at any time there is any doubt about anyone's safety, the operator has the authority to stop and refuse to continue the operation.
B. If loose items are placed on top of metal decking bundles to be hoisted, these items must be secured to the bundles.
C. Cranes or derricks may be used to hoist employees on a personnel platform provided the provisions of General Industry Safety Orders, Section 5004 are met [excepting subsection (c)] .
D. During the final placing of solid web structural members, the load must not be released from the hoisting line until the members are secured with not less than two bolts drawn up wrench tight, or the equivalent at each connection to sustain anticipated loads and keep objects or structural members from rolling.
1. Structural members used as diagonal bracing shall be secured by at least one bolt per connection drawn up wrench-tight or the equivalent.
2. Double connections are required on columns and/or beam webs over a column.
3. For further information on specific hoisting and rigging stabilization devices and situations, see Title 8, California Code of Regulations, §1710
E. Any beams or other materials being lifted and placed by any hoisting apparatus shall not be released from the hoisting apparatus until the person detaching the load has verified that the load is secured against any unintentional or accidental movement.

: Bracing

A. Trusses and beams must be braced laterally and progressively during construction to prevent buckling or overturning.
1. The first member must be plumbed, connected, braced and/or guyed against shifting before succeeding members are erected and secured to it.
2. The total system must be adequately braced and stabilized to the foundation, to suitable anchors buried in the ground, or by other equivalent methods.
B. Trusses and beams over 25 feet long require an erection plan and procedure prepared by a registered civil engineer, which must be followed and kept available on the job site for inspection by Cal/OSHA.

: Open Web Steel Joists

A. Where steel joists are at or near columns that span 60 feet or less, joists shall
1. be designed to be strong enough for one employee to release the hoisting cable.
2. be set at the same time as the bridging is installed.
3. not be placed on any unstable structure unless the framework has been safely bolted or welded.
B. In steel framing where bar joists are used and columns are not framed in at least two directions with structural steel members, a bar joist must be field-bolted at columns to provide lateral stability during construction.
C. Where 40-foot or longer joists or trusses are used, rows of bridging must be installed to provide lateral stability during construction prior to releasing tension on the hoisting line.
D. Where steel joists are used and columns aren't framed in at least two directions with solid web structural steel members, a steel joist shall be field-bolted at the column to keep it from falling during erection. For more information and further instructions refer to Title 8, California Code of Regulations, §1710.
E. Where the above is not possible, an alternate means of stabilizing joists, designed by a qualified person and indicated in the plan drawings, must be constructed and shop-installed.
F. When steel joists span equal or greater lengths than the span indicated in Tables A and B of the Cal/OSHA Standard, Title 8, Chapter 4:
1. A row of bolted diagonal erection bridging must be installed near the mid span of the joist.
2. Hoisting cables should not be released until the above bridging is installed.
3. No more than one employee can be allowed on this span .
G. Where the span of the steel joists is over 60 feet through 100 feet:
1. Two rows of bolted diagonal bridging must be installed near the third points of the steel joist.
2. Hoisting cables should not be released until the above bridging is installed.
3. No more than two employees can be allowed on this span until all bridging is installed.
H. Where the span of the steel joists is over 100 feet through 144 feet:
1. All rows of bridging shall be bolted diagonal bridging.
2. Hoisting cables should not be released until bridging is installed.
3. No more than two employees can be allowed on this span until all bridging is installed.
I. No changes that affect the strength of a steel joist or joist girder may be made without the approval of the project structural engineer of record.
J. Where the span of the steel joists is over 144 feet, the erection methods used shall be in accordance with the Cal/OSHA Standards, Title 8, Chapter 4; in addition, all steel field-bolted and shop-bolted joists must adhere to these standards
K. [Company] must not place loads on steel joists so that its distribution exceeds the carrying capacity of the joist.
1. The weight of a bundle of joist bridging shall not exceed a total of 1,000 lbs. These bundles must be placed on a mimimum of three joists, the end of which must be positioned one foot away from the end of the secured joist.
2. Metal decking bundles shall be supported in such a way that the load can be unbanded without dislodging the bundles from their supports.
3. No bundle of decking may be placed on steel joists until all bridging has been installed and all joist bearing ends attached, unless ALL of the the following conditions are met:
i. A determination has been made by a qualified, documented authority that this portion of the structure is capable of supporting the load
ii. The bundle is placed on a minimum of three steel joists.
iii. These joists are attached at both ends
iv. At least one row of decking is installed and anchored.
v. Total weight of the decking bundle is not over 4.000 pounds, and
vi. Placement takes place in accordance with the Standards.

:Bolted Diagonal Erection Bridging:

A.The bridging must be indicated on the erection drawing, which must be the primary indicator of the placement of this bridging.
B. Shop-installed bridging clips, or functional equivalents, must be used where the bridging bolts to the steel joists.
C. The nut(s) that bolt(s) two pieces of steel bridging to a steel joist cannot be removed for the attachment of another one.
D. When permanent bridging terminus points cannot be used during erection, additional temporary structures are to be constructed for stability.

: Column Anchorage and Repair

A. Column assemblies must adhere to the standards explicitly described in Title 8, California Code of Regulations, §1710.
1. All columns shall be anchored by a minimum of 4 anchor rods (anchor bolts).
2. Columns must be evaluated by a competent person to determine whether bracing or guying is needed; if so, it shall be installed.
3. Perimeter columns shall not be erected unless they extend a minimum of 48 inches above the finished floor or have holes or other features that permit installation of perimeter safety cables prior to erection of the next tier, except where contstructability does not allow.
B. Repairs:
1. Anchor rods (anchor bolts) must be repaired under the supervision of the project structural engineer.
2. Prior to the erection of a column, the contractor shall provide written notification to the steel erector if there has been any repair, replacement or modification of the anchor rods (anchor bolts) of that column.

: Working and traveling on the skeleton steel of multistory buildings or structures:

A. Tripping hazards: Shear connectors (such as steel studs, bars or lugs), reinforcing bars, deformed anchors, bridging attachments or threaded studs shall not be attached to the top flanges of beams, joists or beam attachments so they protrude vertically or horizontal from the top flange of the member unless another walking/working surface has been installed.
1. When shear connectors are used in construction of floors, roofs and bridge decks, they must be installed after the metal decking is installed, using the metal decking as a working platform.
B. When connecting beams are at the periphery or interior of a structure where the fall distance is greater than 30 feet, ironworkers must be provided with and use a personal fall protection system tied off to either columns, pendant lines secured at the tops of columns, catenary lines, or other secure anchorage points.
1. When performing any other work than connecting, ironworkers must be provided with and use a personal fall protection system when the fall distance is greater than 15 feet, as described in Article 24.
2. When moving from one work point to another, or when releasing slings, ironworkers are permitted to walk the top flange of a beam when the fall distance is 30 feet or less.
3. When the fall distance is greater than 30 feet, ironworkers must coon or walk the bottom flange (inside flange or peripheral beams) or they may walk the top flange if they are tied off to catenary lines.
C. Pendant lines, catenary lines and other lines used to secure workers must be used in accordance with the Construction Safety Orders, Section 1670.
D. If above procedures specified in this section are impractical, perimeter safety nets must be installed of no more than 25 feet below the work surface and extend at least 8 feet beyond the perimeter of the building or structure. Nets shall meet the requirements in Section 1671.
E. For requirements on the various types of floors and temporary floors, please see the regulations in §1710.

: Fall Protection

A. Personal Fall Protection Systems shall be required in accordance with Article 24, §1670 of the California Code of Regulations. Use of a personal fall protection system is required at elevations exceeding 15 feet.

B. Safety Nets: When personal fall protection systems are impractical, approved safety nets must be used in accordance with Article 24, §1671 and 1672.
1.Safety nets purchased on or after 1/1/98 shall be labeled as meeting the requirements listed in (c) Article 24, §1671

C. Employees working on buildings or other structures with large, open spans or areas, such as mill buildings, gymnasiums, auditoriums, hangars, arenas, stadiums and bridges, must be protected from the hazard of falling in accordance with §1669, 1670, and 1671 when the fall height exceeds 30 feet.

D. See "Safety Belts, Personal fall arrest/restraint/positioning requirements" elsewhere in this manual for additional information.

E. All employees subject to these dangers are required to use fall protection equipment as trained at the supervisor's discretion.

F. [Company] must be sure that all employees subject to these dangers are trained on the use of fall protection equipment, including personal fall protection systems, safety nets and any other fall protection devices.

G. Fall protection left by [ Company] in the area where steel erection activity has been completed must be removed, unless the controlling contractor or its representative has asked the steel erector to leave it in place, and has inspected it and accepted the responsibility for supervising it, before any workers enter the area.

: Reinforcing Steel and Similar Projections

A. Employees working at grade or at the same surface as exposed protruding reinforcing steel or other similar projections must be protected against impalement by:
1. Guarding the exposed ends with protective covers, troughs, or caps.
2. The use of guard rails.
3. Approved fall protection systems meeting the design requirements of Article 24, when appropriate.
4. Protective covers as specified in §1712, section (d), which does not allow the use of job-built caps.
5. Employees are not permitted to place or tie reinforcing steel in walls, piers, columns, etc., more than 6 feet above an adjacent surface unless a personal fall protection system is in use.

:Systems Engineered Metal Buildings

A. All of the requirements in this document apply to the erection of these buildings, except those requirements regarding column anchorage and open web steel joists.
B. Each structural column must be anchored by a minimum of four anchor rods or bolts.
C. Rigid frames must have 50% of their bolts (or the # of bolts specified by the manufacturer) installed and tightened on both sides of the web adjacent to each flange before the hoisting equipment is released.
D. Construction loads shall not be placed on unstable supports.
E. In girt and eave strut-to-frame connections, when girts or eave struts share common connection holes, at least one bolt with its wrench-tight nut shall remain connected to the first member (unless otherwise specified by the manufacturer.)
F: Both ends of all steel joists or cold-formed joists shall be fully bolted and/or welded to the support structure before:
1. Releasing hoisting cables
2. Allowing an employee on the joists.
3. Allowing loads on joists.
G. Purlins may only be used as walking or working surfaces when installing safety systems, and after all permanent bridging is installed and fall protection is provided.
H. Construction loads must be placed only within a zone that is a distance of 8 feet or shorter of the center line of the primary support member.

: Roofing

A. Roofing requirements are governed by California Code of Regulations, Title 8, Article 30. A complete copy of these regulations can be found at http://www.dir.ca.gov/.

B. General Safety Requirements:
1. Roof jacks must be constructed to fit the slope of the roof and be designed, fabricated and installed in such a manner that they will sustain all expected loads.
2. Crawling boards must be at least 1 inch thick and 10 inches wide with cleats of at least 1"x2" every 24 inches.
3. When scaffolds are used to protect workers from falls from the edges of roofs, they must be installed and maintained in accordance with Article 22. See "Scaffolds" in your project worksheets.
4. Fall protection is required per Article 24.
5. Ramps and runways must not exceed 20 feet in height and must be at least 40 inches in width.
6. Additional roofing information is available elsewhere in this manual. Employee codes of safe work practice are listed in that section.

: Floor, Roof and Wall Openings
A. These rules apply to any instance where these is danger of employees or materials falling through floor, roof or wall openings, or from stairways or runways:
1. Floor, roof and skylight openings shall be guarded by a standard railing and toe boards or covering.
2. Covering must be capable of supporting twice the weight of the employees, equipment and materials that may be imposed on the cover at any one time.
3. Covering shall be secured against any accidental removal or displacement.
4. Covering shall bear a sign with permanent, legible letters larger than 1 inch high stating: "OPENING- DO NOT REMOVE." Markings with chalk will not apply.
5. The railing must be provided on all exposed sides, except at entrances to stairways.

B. A single 3/8" minimum-diameter wire rope of 13,500 pounds minimum strength must surround the sides of a building and interior openings such as stairways and elevator shafts. This must be located between 42 and 48 inches above the height of the finished floor.
1. Other guard rail protection may be used if sufficient fall protection is provided.
2. Mid rail protection must be installed at the completion of the installation of the deck.
3. If the fall protection surrounding the building is intended for use as a catenary line, it must meet the provisions of Section 1710 [(m)(4)]

: Falling Object Protection:
A. All materials, equipment and tools which are temporarily not in use while work is being done above an altitude of 15 feet shall be secured so they will not accidently drop and injure someone below.
B. At no time shall there be more than four floors or 48 feet of unfinished bolting or welding above the foundation or closest secure floor.

: Temporary Floors
A. For multifloor buildings other than structural steel framed buildings, temporary floors of wood, concrete or other materials must be constructed in accordance with Title 8, Chapter 4, §1635 to protect workers from falling through joists or girders, and from the dangers of falling substances.
1. No person shall proceed with or permit any other person to proceed with any work until this flooring is in place.
2. On buildings where temporary floors are not possible, and where scaffolds or approved fall protection isn't used, safety nets shall be installed and maintained whenever the potential fall distance exceeds two stories or 30 feet, whichever is less, as required according to Article 24, §1671 and 1672.
3. When gathering and stacking temporary floor planks from the last panel, the employee must be wearing an approved personal fall protection device attached to a catenary line or other substantial anchorage.

B. For multifloor structural steel framed buildings more than 2 stories high erected in tiers or stories (but not buildings having large open spans such as gymnasiums or stadiums) the following shall apply:
1. Temporary floors of wood, concrete, equivalent strength metal decking or other materials must be constructed in accordance with Title 8, Chapter 4, §1635
2. Fall protection shall be required according to Article 24, no matter how short the duration of the job.
3. Materials of sufficient strength as designated by Section 1632(b) must be provided in areas not covered by planking to provide fall protection and prevent falling objects.
4. For information on installing safe floor planking, refer to "floor planking" in your Worksheet.
 

HOME